Sign in to start your free trial — 1 XER upload included.
Sign In
Sign Up
Trial accounts get 1 free XER programme upload. No card required.
New Railway Project
Physical Progress
Financial Progress
Delay (days)
Health
Project Start
Contract mobilisation
Baseline Finish
Original contract
Forecast Finish
● As of Data Date
Not set
Project Cost
Not set
Sanctioned budget
Actual Cost
Pending
Project Status
Overall Progress
0%
actual
Health: —
Scheduled %
SPI
Phase Progress
S-Curve — Planned vs Actual & ETC
Planned Actual ETC1 ETC2
Scenario 1 — Current rate
Scenario 2 — Required rate to finish on time
Both scenarios — gap = recovery effort
Red = delay  ·  Purple = recovery
affects ETC2
Driving Activities
EVM Metrics
Budgeted Cost (BAC) ₹ Cr
Actual Cost (AC) ₹ Cr
PV
Planned Value
BAC×%sched
Planned Value
Budgeted cost of work scheduled to be done by data date.
PV = BAC × %sched
EV
Earned Value
BAC×%actual
Earned Value
Budgeted cost of work actually completed to date.
EV = BAC × Physical %
AC
Actual Cost
User input
Actual Cost
Real cost incurred for work performed to date.
AC = User input
CPI
Cost Perf. Index
EV÷AC
Cost Perf. Index
>1 under budget · =1 on budget · <1 over budget.
CPI = EV ÷ AC
SPI
Sched. Perf.
EV÷PV
Schedule Perf.
>1 ahead of schedule · =1 on schedule · <1 behind.
SPI = EV ÷ PV
CV
Cost Variance
EV−AC
Cost Variance
Positive = under budget. Negative = over budget.
CV = EV − AC
SV
Sched. Variance
EV−PV
Schedule Variance
Positive = ahead of plan. Negative = behind plan.
SV = EV − PV
EAC
Est. at Completion
BAC÷CPI
Est. at Completion
Forecast of total project cost at current cost performance rate.
EAC = BAC ÷ CPI
Enter BAC and AC above to activate cost performance metrics.
Contract Milestones
Activity Status
Schedule Settings
Project Start
Data Date
Scheduling Logic
Default Calendar
Display Settings
Font
Font Size
Row Height
Band Colours
VEDAM Railway Project Intelligence ANALYTICS MODULE
SPI & delay trajectory over data dates
SPI — Latest
Set a data date
Delay — Latest
vs baseline
Progress — Latest
Physical % complete
Trend
⚡ Trend Analysis
Click ↺ Refresh to load analytics.
SPI Over Time — Schedule Performance Index
Delay Accumulation — Days Behind Baseline
Planned vs Actual Progress — % Complete
Critical Activity Count — Over Time
Click ↺ Refresh to build heatmap.
Add Activity Slip
Global Assumptions
Resource efficiency (%) 100%
Below 100% = reduced productivity (monsoon, site access). Above 100% = acceleration (overtime, extra crews).
Impact on Project Finish
Baseline Finish
Saved baseline
Forecast Finish
Current schedule
What-If Finish
With your changes
Required SPI
To finish on baseline
Forecast S-Curve — Baseline vs What-If
Cascading Impact — Activities affected by your changes
Add an activity slip to see cascading impact on downstream activities.
Schedule Intelligence
Last computed: —
Schedule Narrative
Auto-generated from CPM data · Run Reschedule to refresh
Run Reschedule to generate narrative
VEDAM · Estimator
0  hrs
Total Design Hours
Hours / km
Total Project Cost
Cost / km
Confidence
Core Inputs
Estimate Confidence
Fill Additional Input tab to refine. Save icon captures snapshot.
Total Design Hours
Hours per km
Normalised intensity
Effort by Discipline
Grade Split
Propagates km & stations → CPM durations → reruns schedule
Additional Inputs Each section refines the estimate
Disciplines in Scope
Toggle on/off. Deactivating removes discipline from estimate entirely.
Route & Configuration
Line type, % elevated/underground, depot
Site & Physical Conditions
Terrain, geotechnical, bridges, tunnels
Technical Complexity
Signalling, BIM level, electrification
Project Context & Schedule
Review cycles, survey data, dates
Total Design Hours
Hours per km
Normalised intensity
Heaviest Discipline
Estimate Confidence
Effort Pyramid — Grade Split
Top Cost Drivers
Grade Mix
Discipline Intensity Heatmap
Full Hours Breakdown
DisciplineDirectorSenior Mid-SeniorJuniorTotal hrs/kmShare

₹ Construction Cost Estimate
Unit Rates — per km (₹ Cr)
Per-Unit Costs (₹ Cr)
Reference Anchor
30 km · 20 stn · 1 depot · Elevated · ₹14,820 Cr · ~104w
Cost Breakdown
Phase Cost Profile
Factor Analysis
Discipline Multipliers
Active Weight Factors
Effective Multiplier per Discipline
Iteration Log
Estimate Evolution
No snapshots yet.
Grade Mix Evolution
No snapshots yet.
All Snapshots
Save your first snapshot using the save icon on Core Input tab.
Railway Project Intelligence
EOT & Delay Analysis
Contract Protocol Compensation Event — Clause 60.1 · PM assessment
Add Delay Event
Event Reference
Event Description
Responsible Party
Compensation Event Type
Impacted Activity
Delay Duration (working days)
Event Start Date
Notified?
Delay Event Register 0 events
📋
No delay events recorded
Add delay events using the form above. Each event will be analysed for CPM impact and EOT entitlement.
Add a delay event to begin analysis
Each event is analysed against the CPM schedule. Impacted activities, float consumption, and critical path effect are calculated automatically.
Window Analysis — Delay Apportionment by Period
Window analysis divides the project into time windows and identifies which delay events were operative in each window, the dominant delay cause, and the party responsible. This forms the basis for concurrent delay analysis under NEC4 — Clause 60.1.
WindowPeriodPlanned Finish Actual/ForecastDelay (d) Dominant CauseResponsibleConcurrent?
📊
Add delay events to generate window analysis
Windows are automatically created around each delay event, showing which delays were concurrent and the dominant responsible party per period.
Retrospective Analysis — Longest Path & Collapsed As-Built
Uses the Actual Start / Actual Finish dates already recorded per activity (Activity Details panel) — no separate as-built entry required. Retrospective methods per SCL Delay & Disruption Protocol (2nd Ed.) and AACE RP 29R-03. These are typically used in dispute/adjudication review, not routine prospective compensation-event assessment — see the note on each panel for contract-specific fit.
Retrospective Longest Path
"What was the as-built critical path to completion, viewed retrospectively?" — traced backward from whichever completed activity finished last, through whichever predecessor left zero gap before its successor's actual start.
Collapsed As-Built ("But-For")
Removes recorded delay events one at a time from as-built durations to see the completion date collapse toward what it would have been but for those events.
Order-sensitive. Removing the same events in a different sequence can change how delay is apportioned between parties, even though total delay recovered is identical — a documented limitation of this method (AACE RP 29R-03), not a tool defect. The comparison below shows both orders side by side; don't quote one order's split without disclosing which was used.
Removal order:
Order Sensitivity Check
No completed activities or delay events yet
Retrospective Longest Path needs at least one activity with both Actual Start and Actual Finish set. Collapsed As-Built needs delay events tied to activities with recorded durations.
⚖️
No entitlement computed yet
Add employer-caused delay events to compute EOT entitlement. Contractor-caused and neutral events are shown but do not attract EOT.
📄
Claim narrative will appear here
Add delay events and compute EOT. The system will generate a structured claim narrative referencing the correct contract clauses for your chosen protocol.
📋 Progress Report
Fetching from schedule…
§1Cover Page
Signature Block
§2Project Summary
↺ Overall progress, start/finish dates and delay auto-fetched from schedule
Overall Progress (auto)
Forecast Finish (auto)
§3Physical Progress
↺ Planned % and Actual % auto-calculated from schedule activities per WBS group
WBS / DisciplinePlanned%Actual%Last Period%
§4Schedule Status
↺ SPI, delay days, critical activities auto-fetched from CPM engine
SPI (auto)
Delay Days (auto)
§5Cost Status & EVM
§6Issues & Risks
§7Next Period Plan
\n
New Project
Load Sample Project
Split:
Ch: Time:
Activities
No activities.
Use + Activity or load a sample.
X · Chainage (km)  /  Y · Date  /  Slope = production rate ⚠ conflicts
Data Date:
Activity Detail
Click an activity line
to view and edit details.
0 activities Stations: 0 Infra: 0 ⚠ conflicts
Project Settings
Project
Project Name
Corridor
Total Length (km)
Y Axis
Chainage Start (km)
Chainage Interval (km)
View Window
TLC Start Date
TLC End Date
Project Start Date
Data Date
Time Axis Tiers
Number of tiers (1–3)
Tier 1 (outermost)
Tier 2
Tier 3 (innermost)
Season Band — only enabled seasons display
Monsoon
Winter
Summer
⚠ Risk Register
ID Category Description P I Score Residual Status Owner Mitigation
No risks recorded. Click + Add Risk to begin.
0
Total Risks
0
Open
0
High (≥15)
0
Closed
Risk Heatmap (P × I)
Low (1–4)
Medium (5–9)
High (10–24)
Very High (25)
P = Probability (1-5) · I = Impact (1-5)
⏱ Delay Analysis Register
📌 Delay Analysis Register — Log delay events, classify by responsibility, and record concurrent delay. This register feeds into §3 Schedule Status of the Progress Report. EOT quantum is auto-summed per classification.
0d
Employer Risk
0d
Contractor Risk
0d
Neutral / Force Majeure
0d
Net EOT Entitlement
ID Activity Event Description Start Date End Date Delay (d) Classification Concurrent? Concurrent Days Net Days Clause Ref Status
No delay events recorded. Click + Add Delay Event to begin.
⊞ Column Chooser
✏️Edit Activity
Add Activity Below
⬆️Add Activity Above
Move to WBS...
🗑Delete Activity
Enable 📋 Activity Details in toolbar, then click any activity
⬆ Import from Primavera XER
📂
Drop your .XER file here
Or click to browse  ·  Primavera P6  ·  Any version  ·  Works offline
Reading XER file...
0
Activities
0
Relationships
0
Critical
0
Neg Float
Activity Preview (first 20)
IDNameDur(d)Float(d)TypeStatus
Importing will replace your current schedule. The XER activities will be mapped to VEDAM format and a full CPM reschedule will run automatically.
After Import
⚠ For a progressed XER, use target dates as baseline — these are the original as-planned dates stored in P6 (target_start / target_end), independent of actual progress. Using CPM baseline on a progressed schedule will corrupt your slip analysis.
⬇ Export Schedule
Choose Export Format
📊
Excel
Full CPM data with float values and colour coding
.xlsx
🗂
Primavera XER
Re-import into P6 — full round-trip
.xer
📄
MS Project XML
Open directly in Microsoft Project
.xml
Export Summary
📋 Loading...
🔗 Loading...
🔴 Loading...
📅 Loading...